The work on Main Rice Mills has entered into a new phase. February 22, 2012
Mill Civil Works have now been significantly completed to start the phase of PEBs erection. In this regard, the erection phase LC for Mabani Steel has already been opened by SSAD, meeting all formalities for them to commence erection work. Presently, the construction team is busy in making steel forms for the cantilever slab. The slab work of entrance end of the span has been completed. Third intake pit was also completed and preparations were being to pour slab concrete around this area. Adam Construction requires moving the PEB equipment away from slab for aligning and placing Anchor Bolts for PEBs. |
|